How do I get electricity during construction of my home/business?

At the time a building permit is being obtained, construction power must be requested. If construction surpasses the rough topout state, construction power will not be issued. Temporary construction power may be secured for a residence at the time of permit application for the residence by mentioning to the building safety counter person that temporary construction power is needed.

Once the building permit for the residence is issued, should the applicant need construction power, a “field change” may be issued by the building inspector. In either case, the applicant will receive instructions on setting up a temporary construction service and will be given the appropriate forms to fill out and sign. Temporary construction power for a business is left up to the discretion of the building inspector, since he/she will be more familiar with the project.